Power Up

This section describes powering up and initializing the Tellabs OLT2.

  1. Insert the 8-pin molex power cable into the power input socket at the back of the Tellabs OLT2.
    Information Note: The Tellabs OLT2 does not have a power on/off switch, as it is not intended to power down the shelf while it is in service. Inserting the power cable will cause the unit to power up.
  1. Approximately 7 seconds after inserting the power cable, the FAIL LED illuminates RED, the ACTV LED illuminates GREEN and the cooling fans for the shelf start.
  2. During the power-up diagnostics, the ACTV LED blinks GREEN at a 0.5-second interval and the FAIL LED remains red. This is followed at a time later, by the ACTV LEDs blinking GREEN at a 0.5 second interval.
  3. Upon completion of initialization, the ACTV LED illuminates GREEN, the FAN STAT illuminates GREEN, and the FAIL LED goes dark.
  4. The initialization takes 2 - 3 minutes to complete.

LED Status

LEDs OLT2
Without Existing Data
(Has not completed a turnup)
with Existing Data
(Has previously completed a turnup)
ACTV Blinking GREEN GREEN
FAIL RED Dark 
FAN STAT RED GREEN
  1. Do the ACTV, FAIL LEDs, and FAN STAT illuminate, as described in Step 5.
  • If YES, go to Step 7.
  • If NO, contact the Tellabs Technical Assistance Center (TAC) for assistance. 
  1. Proceed to TurnUp the OLT2.