Power Up the OLT1
This section describes powering up and initializing the Tellabs OLT1.
- Insert the power cable into the power input socket at the back of the Tellabs OLT1. Connect the other cable lead into a 120/240 VAC outlet or use a 208V/240V outlet to power up the unit, within the European Union.

Note: The Tellabs OLT1 does not have a power on/off switch, as it is not intended to power down the shelf while it is in service. Inserting the power cable will cause the unit to power up.
- Approximately 7 seconds after inserting the power cable, the STAT OLT CPU and STAT PON CPU LEDs illuminate RED, the ACT LED illuminates GREEN and the cooling fans for the shelf start.
- During the power-up diagnostics, the STAT OLT CPU LED blinks GREEN at a 0.5 second interval and the ACT LED goes dark. This is followed at a time later, by the STAT PON CPU LEDs blinking GREEN at a 0.5 second interval.
- Upon completion of initialization, the LEDs illuminate as described in the Table below. The initialization takes 2 - 3 minutes to complete.
LED Status
| LEDs |
OLT1 | |
|
without Existing Data
(Has not completed a turnup)
|
with Existing Data
(Has previously completed a turnup)
|
|
| STAT OLT CPU | Blinking GREEN | GREEN |
| STAT PON CPU |
Blinking GREEN |
GREEN |
| ACT | Dark | GREEN |
- Does the STAT OLT CPU, STAT PON CPU, and the ACT LEDs illuminate, as described in Step 4.
- If YES, go to Step 6.
- If NO, contact the Tellabs Technical Assistance Center (TAC) for assistance.
- Refer to Maintenance for instructions.
- Proceed to Turn Up the Tellabs OLT1?